Project Description
PROJECT | Completion of Kifisos River rehabilitation between Posidonos Av. and Solomou str. (chainnage 0+000 – 0+700) at Moschato |
OWNER | Ministry of Public Works |
PROJECT CONTRACTOR | J/V PARNON S.A. – EUROPAIKI TECHNIKI S.A. |
GEOTECHNICAL INVESTIGATION CONTRACTOR | GEOCONSULT Ltd. |
DATES OF GEOTECHNICAL INVESTIGATION | November 1997 – January 1998 |
The project is located at the part of Kifisos River between the coastal Ethnarxou Makariou Avenue (chainnage 0+000) and Solomou str. (chainnage. 0+700), at the Moschato area. The project includes the rehabilitation of Kifisos River bed between chainnage 0+000 and chainnage 0+700.
Drilling 13 exploratory boreholes (9 on-shore and 4 inside the river) of a total length of approximately 350 m, with the corresponding laboratory tests, preparation of a factual and interpretive report and proposals for excavation retaining structures with sheet pile walls, controlling ground water with jet grouting and controlling Kifisos River waters with embankments and rerouting pipes.
Comments are closed.